Safety Management Standard for Bowl Button Scaffolding

Plan preparation: A special construction plan must be prepared, and detailed design calculations should be carried out for key parts such as foundations and connecting wall members in the plan.

swivel scaffolding

If a floor standing steel pipe scaffold with a height of 24M or more is erected, the special construction plan must be approved by experts before implementation.

The plan should specify key parameters such as the layout of the scaffolding, spacing between uprights, step distance, setting of connecting wall components, and arrangement of diagonal braces.

.