6 key points for the acceptance of scaffolding wall connecting components, must see for construction site acceptance!

This is the wall connecting component of the scaffold, which needs to be inspected and accepted before pouring concrete.

cuplock scaffolding components

The following six points should be considered: the depth of the first pre embedded short pipe embedded in the concrete beam should not be less than 300mm.

.