Construction technology and safety briefing for the installation of steel cantilever external scaffolding

This project is a residential building with reinforced concrete shear wall structure, with 26 floors above ground and a standard floor height of 2.

9 meters.

Starting from the top plate of the 4th floor structure, a steel cantilever external scaffold is used.

combination wing nut

The cantilever I-beam is made of 18 # I-beam and is erected section by section, with each section not exceeding 20 meters high.

It is divided into six sections for cantilever.

This disclosure is applicable to the pre embedding, installation, lifting and leveling of the steel cantilever external scaffolding in this project, as well as daily use management.

According to the “Safety Technical Code for Steel Pipe Scaffolding with Fasteners in Construction” JGJ130-2011, “Unified Code for Safety Technology in Construction” GB50870-2013, and special construction plans.

.