“Leisurely landscaping construction progress of Zhumadian Xinhui residence is reported as follows:” 01 – the progress of Zhumadian Xinhui residence is as follows: manual cleaning of pump pit, earthwork reinforcement fabrication, binding of bottom plate and wall reinforcement are completed, 70% of external network installation and backfilling are completed, and a sewage pipeline on the west side of 13# building is completed..
Ministry of housing and urban rural development: epidemic prevention costs can be included in the project cost! The person in charge of construction / construction / supervision project is the first responsible person for epidemic normalization prevention and control
[construction settlement] construction teams in rural residential areas shall be settled free of charge