“Leisurely landscaping construction progress of Zhumadian Xinhui residence is reported as follows:” 01 – the progress of Zhumadian Xinhui residence is as follows: manual cleaning of pump pit, earthwork reinforcement fabrication, binding of bottom plate and wall reinforcement are completed, 70% of external network installation and backfilling are completed, and a sewage pipeline on the west side of 13# building is completed..
The construction party requires the manager to issue a written guarantee for the priority of project funds. Otherwise, what should be done if the construction party refuses to deliver the built project and does not cooperate with the project acceptance?