The latest progress in the construction of North China Oilfield in Bayannur is coming! 30 wells are planned to be drilled

Hetao Basin is covered with good Cenozoic caprock, which has the characteristics of near oil source, short-distance migration and good sealing system.

Linhe 3D exploration project is mainly aimed at the central fault and periphery of the main structure area, with a full coverage of 1200km ²。 The administrative division of the work area is subordinate to Linhe District, Hangjinhou banner, Dengkou county and Wuyuan County of Bayannur City, Inner Mongolia Autonomous Region, of which Linhe District accounts for about 76.7%.

According to previous news reports, in 2018, PetroChina Huabei Oilfield Company entered Hetao exploration area for construction and found three 100 million ton reserves areas of Jilantai, Nalin lake and Xinglong in only three years.

At present, the Linhe depression in Hetao Basin has achieved an overall breakthrough in exploration.

Text and video: Wang Jiacheng, Dai Yongzhi, Wang Ting, edited by: Wang Jing, proofread by: Ge Xihe, Fan Jie, Dangqi, Liu Shiya, reviewed by: Chen Huankun, final review: Zhang Haibin’s past review ◆ latest announcement! These two batches of drugs do not meet the regulations! ◆ Bayannur City has signed cooperation agreements with two banks, involving new energy, industrial transformation, rural revitalization, etc ◆ the “blacklist” of off campus training institutions in Linhe district is published..

Fixing Socket Cross Hole

It is a favorable area for oil and gas exploration.

In order to expand the exploration results and accelerate the realization of this goal, PetroChina deployed Linhe 3D seismic exploration and acquisition project in 2021, It is of great significance for seeking further oil and gas exploration and large-scale reserve production in the exploration area, providing sufficient oil and gas resource support for local economic development and ensuring national energy security.

It is understood that the drilling construction project will also be the capital of our city Land farmers and herdsmen provide jobs.

In the next step, the development of Linhe area will achieve the established goal according to the two-step strategy, build an output of 1 million tons by the end of 2023, and continue to expand exploration to ensure resource replacement, so as to ensure the long-term stable production of 1 million tons of oil fields.

Due to winter construction reasons, the construction unit established a winter construction leading group to increase front-line operators, from two shifts to three shifts, increase the rest frequency of operators in severe cold weather, and carry out emergency knowledge training and practice to improve the emergency rescue and disposal capacity.

Recently, the reporter learned from Bayannur branch of Huabei oilfield that Bohai Drilling, great wall drilling, CNPC logging CNPC transportation and other construction units plan to drill 30 wells (including 8 pre exploration and evaluation) in Linhe, test 7 wells, 16 layers and shoot 16 wells.

The planned construction time is 2 months (December 1, 2021 to February 1, 2022).

Since September this year, the employment agency of Linhe District Employment Service Center has recruited more than 30 local agricultural and animal husbandry migrant workers for Bayannur branch of Huabei Oilfield.