Special Construction Plan for Suspended Scaffolding

The above ground external frame of this project adopts a cantilever type steel pipe scaffold, which serves as a structural scaffold, external wall masonry and plastering operation frame.

During the decoration phase, the external frame will be removed and the suspended basket frame will be used to complete the soil material construction.

The vertical distance of the frame upright pole is 1.

8m, the horizontal distance is 1.

05m, and the step distance is 1.

5m.

The cantilever steel beam for general parts is selected as 18 # I-beam, and for special parts it is 22 # I-beam.

The installation parameters are detailed in the table below.