Housing and Urban Rural Development Bureau: Starting from March 15th, a special rectification of scaffolding engineering will be carried

Recently, the Housing and Urban Rural Development Bureau of Foshan City has decided to carry out a special renovation of construction scaffolding for housing construction projects throughout the city from March 15, 2024 to September 30, 2024 (hereinafter referred to as the special renovation)..

Slab Props

1. Enterprise security management situation. The responsible parties involved in the construction project have implemented the “Regulations on Safety Management of Sub projects with High Risk” (Order No. 37 of the Ministry of Housing and Urban Rural Development), the “Notice of the General Office of the Ministry of Housing and Urban Rural Development on Relevant Issues Concerning the Implementation of the Regulations on Safety Management of Sub projects with High Risk” (Jianbanzhi [2018] No. 31), and the “Construction Safety Inspection Standards” (JGJ59-2011); The establishment of a quality and safety assurance system on the construction site, the performance of management personnel such as project leaders of the construction unit, project managers and technical leaders of the construction unit, and project directors of the supervision unit on duty, as well as the allocation and performance of full-time safety management personnel on the construction site..

2. Plan preparation and approval status. Whether the content of the special construction plan for scaffolding is comprehensive, whether it follows the approval process of construction and supervision unit review in accordance with the Safety Management Regulations for Sub projects with High Risk, and whether the special construction plan for scaffolding and formwork support projects in hazardous projects exceeding a certain scale is subject to expert argumentation in accordance with the prescribed requirements..

3. Enterprise qualifications and personnel management situation. Whether the engineering project has subcontracted professional engineering to qualified contracting enterprises (template scaffold professional contracting qualifications) in accordance with regulations, and whether on-site scaffold operators have obtained special operation qualification certificates for construction scaffolding..

4. Material entry inspection and acceptance status. When materials such as steel pipes, fasteners, adjustable brackets, and dense mesh are used in the construction of the frame, are witness sampling conducted according to batches and sent to qualified testing institutions for testing; Whether the materials for template support and scaffolding engineering are inspected before installation, and whether all parties involved in the construction verify the witness sampling witness records and entry inspection reports when entering the site. Spot check the appearance of materials such as rust, cracks, deformation, product identification, as well as the main dimensions such as inner and outer diameters and wall thicknesses of the materials..

5. Construction process management situation. Before setting up or dismantling scaffolding, whether the on-site management personnel have been briefed on the construction plan according to the special construction plan and relevant regulations and standards, whether the on-site management personnel have provided safety technical briefing to the operating team and operators, signed and confirmed, and formed data archives; Whether the construction unit (professional contracting unit) strictly organizes construction according to the special construction plan, whether the full-time safety management personnel of the project supervise the installation process on site, and whether the supervision unit conducts inspections of the installation or demolition operation site..

6. Construction acceptance management situation. Whether to organize inspection and acceptance of the installation of scaffolding and formwork support at each stage according to regulations and specifications, retain information and archive it. Conduct spot checks on the stability, standardization, and safety of the scaffolding and formwork support engineering entity, and ensure compliance with technical specifications and relevant standards. Whether monitoring is carried out according to regulations for those that need to be carried out after the installation is completed..

(1) Self inspection and self correction stage (March 15th to 4th).