Special rectification work plan for construction scaffolding of housing construction projects in Foshan City

On March 12th, the Housing and Urban Rural Development Bureau of Foshan City issued a notice on the issuance of the special rectification work plan for construction scaffolding in housing construction projects in Foshan City..

Prop Sleeve

Our bureau has decided to carry out the special rectification of construction scaffolding for housing construction projects throughout the city from March 15, 2024 to September 30, 2024 (hereinafter referred to as the special rectification)..

(1) Self inspection and self correction stage (March 15th to April 30th)..

(2) Inspection and supervision stage (May 1st to August 31st). We should highlight the supervision and inspection of key enterprises and projects. The problems and hidden dangers discovered during inspection must be rectified within a specified period of time and managed in a closed-loop manner. Our bureau will adopt the “four no’s and two’s” approach to supervise and inspect the self inspection and self correction of projects and the implementation of special rectification by various district bureaus, and notify them..

(3) Summary and analysis stage (September 1st to September 30th)..

Each district bureau should increase its law enforcement and supervision efforts. Scaffolds with problems in stacking and using materials on construction sites, projects that have not been reviewed and reviewed according to regulations, and construction projects that have not been erected should be suspended for rectification, and credit points should be deducted;.

For illegal activities involving hazardous projects, punishment shall be imposed in accordance with the relevant provisions of the Safety Management Regulations for Sub projects with High Risk..

The responsible parties involved in the construction project have implemented the “Regulations on Safety Management of Sub projects with High Risk” (Order No. 37 of the Ministry of Housing and Urban Rural Development), the “Notice of the General Office of the Ministry of Housing and Urban Rural Development on Relevant Issues Concerning the Implementation of the Regulations on Safety Management of Sub projects with High Risk” (Jianbanzhi [2018] No. 31), and the “Construction Safety Inspection Standards” (JGJ59-2011);.

The establishment of a quality and safety assurance system on the construction site, the performance of management personnel such as project leaders of the construction unit, project managers and technical leaders of the construction unit, and project directors of the supervision unit on duty, as well as the allocation and performance of full-time safety management personnel on the construction site..

Whether the content of the special construction plan for scaffolding is comprehensive, whether it follows the approval process of construction and supervision unit review in accordance with the Safety Management Regulations for Sub projects with High Risk, and whether the special construction plan for scaffolding and formwork support projects in hazardous projects exceeding a certain scale is subject to expert argumentation in accordance with the prescribed requirements..

Whether the engineering project has subcontracted professional engineering to qualified contracting enterprises (template scaffold professional contracting qualifications) in accordance with regulations, and whether on-site scaffold operators have obtained special operation qualification certificates for construction scaffolding..

When materials such as steel pipes, fasteners, adjustable brackets, and dense mesh are used in the construction of the frame, are witness sampling conducted according to batches and sent to qualified testing institutions for testing;.

Whether the materials for template support and scaffolding engineering are inspected before installation, and whether all parties involved in the construction verify the witness sampling witness records and entry inspection reports when entering the site. Spot check the appearance of materials such as rust, cracks, deformation, product identification, as well as the main dimensions such as inner and outer diameters and wall thicknesses of the materials..

Before setting up or dismantling scaffolding, have the on-site management personnel been briefed on the construction plan and relevant standards in accordance with the special construction plan? Have the on-site management personnel communicated the plan to the operating team and operators.